Queen Mary Repair work continues

The City of Long Beach has begun preparation work for the installation of anticipated new boilers and heat exchangers onboard RMS Queen Mary.

The multi-phase project, which began in late January with the demolition of the existing heat exchangers, piping and electrical pneumatics, is part of the last round of critical repairs required to reopen the Queen Mary’s hotel, restaurants, bars and other onboard amenities this spring.

Demolition work is underway for the ship’s existing, out-of-commission boilers and heat exchangers and is expected to be completed over the next few weeks, at which point installation of the new piping and mechanical equipment that support the new boilers and heat exchangers will take place. The new boilers and heat exchangers can then be installed.

Once installation of the new boilers and heat exchangers is complete, which will supply hot water for cooking, cleaning, sanitizing and other hospitality amenities, Evolution Hospitality staff can begin preparations to reopen additional elements of the Queen Mary, such as the hotel, restaurants, bars and shops onboard.

The remainder of the critical repairs approaching completion includes the installation of an emergency generator, which powers critical components of the ship in the event of an emergency, and the completion of the bilge pump system that is also designed to protect the ship in case of an emergency. The installation of the generator and bilge pump system is expected to be completed by early spring.

Other projects that are taking place concurrently and are anticipated to be complete prior to a broader reopening include upgrades to the ship’s main boarding entrance – such as repairs to the Wharf and Promenade Deck gangways; elevator repair and modernization; and painting, lighting and other enhancements to the entire Wharf area – as well as onboard restroom repairs, flooring replacements and ceiling paint and tile repair in the Promenade Deck’s Main Hall; HVAC repair and floor and window repairs in the Observation Bar; parking lot repairs; and kitchen and restaurant improvements, among others.

Ships Montly - January 2024

Damen launches fully electric Tug for Port of Antwerp-Bruges

On 12 April 2024 Damen Shipyards Group launched the second of its fully electric RSD-E Tugs 2513 at Damen Song Cam Shipyard. The tug...
Advertisement

Related articles

Damen launches fully electric Tug for Port of Antwerp-Bruges

On 12 April 2024 Damen Shipyards Group launched the second of its fully electric RSD-E Tugs 2513 at...

MV Balmoral moves to dry dock

As scheduled, on 17 April 2024 the preserved motor vessel Balmoral left her berth at M Shed in...

Polsteam’s latest bulkers enter service

Polsteam Koprowo, the second in a series of 12 lakermax bulkcarriers, has entered service with Polish ship owner...

New Cunarder Queen Anne makes her debut

Cunard's newest cruise ship, Queen Anne, arrived at her home port of Southampton on 30 April 2024. The...