Queen Mary Repair work continues

The City of Long Beach has begun preparation work for the installation of anticipated new boilers and heat exchangers onboard RMS Queen Mary.

The multi-phase project, which began in late January with the demolition of the existing heat exchangers, piping and electrical pneumatics, is part of the last round of critical repairs required to reopen the Queen Mary’s hotel, restaurants, bars and other onboard amenities this spring.

Demolition work is underway for the ship’s existing, out-of-commission boilers and heat exchangers and is expected to be completed over the next few weeks, at which point installation of the new piping and mechanical equipment that support the new boilers and heat exchangers will take place. The new boilers and heat exchangers can then be installed.

Once installation of the new boilers and heat exchangers is complete, which will supply hot water for cooking, cleaning, sanitizing and other hospitality amenities, Evolution Hospitality staff can begin preparations to reopen additional elements of the Queen Mary, such as the hotel, restaurants, bars and shops onboard.

The remainder of the critical repairs approaching completion includes the installation of an emergency generator, which powers critical components of the ship in the event of an emergency, and the completion of the bilge pump system that is also designed to protect the ship in case of an emergency. The installation of the generator and bilge pump system is expected to be completed by early spring.

Other projects that are taking place concurrently and are anticipated to be complete prior to a broader reopening include upgrades to the ship’s main boarding entrance – such as repairs to the Wharf and Promenade Deck gangways; elevator repair and modernization; and painting, lighting and other enhancements to the entire Wharf area – as well as onboard restroom repairs, flooring replacements and ceiling paint and tile repair in the Promenade Deck’s Main Hall; HVAC repair and floor and window repairs in the Observation Bar; parking lot repairs; and kitchen and restaurant improvements, among others.

Ships Montly - January 2024

Two Damen Combi Freighters 3850 launched for Fast Lines

On Friday 30 May 2025 the second of three Damen Combi Freighters (CF) 3850 was launched in China for Fast Lines Belgium. This follows...
Advertisement

Related articles

Two Damen Combi Freighters 3850 launched for Fast Lines

On Friday 30 May 2025 the second of three Damen Combi Freighters (CF) 3850 was launched in China...

Stena Line Invest £17 Million In Birkenhead Port Development

Swedish ferry company, Stena Line is investing £17 million into developments at the 12 Quays Terminal in Birkenhead...

UKD host naming of new dredger UKD Sealion

UK Dredging (UKD), a division of Associated British Ports (ABP), hosted the official naming ceremony for the UKD...

MPCC feeder ships to run on low carbon bio-methanol

NCL Nordland, the second of two container vessels that put bio-methanol at the forefront of container shipping’s low...