Sea Installer upgraded at Damen Shiprepair Amsterdam

Damen Shiprepair Amsterdam (DSAm), part of Damen Shiprepair & Conversion, is currently undertaking a major modification and maintenance project on the jack-up vessel Sea Installer.

In what is a multidisciplinary project, the yard’s primary focus will be to upgrade the vessel’s main crane. With her increased lifting capacity, the 132m A2SEA-owned vessel, which is used chiefly for offshore wind farm installation purposes, will be able to take on a broader scope of work as offshore wind activities involve heavier and larger components.

Arriving at DSAm on 10 April 2016, Sea Installer took her position alongside lay-by berth number 1. The smooth running of this project is facilitated by the prefabrication of key components at nearby Niron Staal Amsterdam, also part of Damen Shiprepair & Conversion.

Niron Staal fabricated and supplied the new boom rest, hook block pockets, trolley rail and support stools. With these parts ready from the outset, DSAm was able to commence the project at maximum capacity.

The Sea Installer project also involves some notable lifting procedures: DSAm has created a temporary lifting and storage area alongside the vessel’s berth to accomplish these safely and effectively. “We need to remove a total of 569 tonnes from the vessel and lift a further 702 tonnes back on board again,” explains Damen Project Manager Daniel Gerner.

????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????
????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????
Ships Montly - January 2024

Seaspan Energy launches the Seaspan Lions LNG bunkering vessel

Seaspan Energy has launched the second of its three 7600m3 LNG bunkering vessels, Seaspan Lions, named after the twin peaks of the North Shore,...
Advertisement

Related articles

Seaspan Energy launches the Seaspan Lions LNG bunkering vessel

Seaspan Energy has launched the second of its three 7600m3 LNG bunkering vessels, Seaspan Lions, named after the...

Agreement reached to build new hospital ship for Mercy ShipsAgreement reached to build new hospital ship for

A groundbreaking agreement between MSC Group, MSC Foundation and the charity Mercy Ships International has been reached for...

Barfleur trials in Guernsey go without a hitch

Brittany Ferries' cruise ferry Barfleur successfully carried out berthing trails in St Peter Port on 24 April 2024....

Ships Monthly May 2024 issue out now.

The May 2024 issue of Ships Monthly is out now, and is packed with all the usual news...