Advertisement

Cape Town port dredging to improve access

Transnet National Ports Authority (TNPA)’s Dredging Services division has embarked on a R15 million (US$ 1.1m) maintenance dredging campaign at the Port of Cape Town to restore the design depths inside Duncan dock.

The maintenance campaign, which began on 8 March 2017, is scheduled for completion by the end April 2017. The main objective of the dredging campaign is to ensure the Port of Cape Town provides safe navigational channels and berthing facilities for shipping by restoring the original design depths.

Two dredging vessels, the Isandlwana, a Trailing Suction Hopper Dredger and the Italeni Grab Hopper Dredger have been mobilised by TNPA Dredging Services for this purpose. Multi-beam bathymetric surveys are conducted at regular intervals throughout the campaign that will ensure all areas within Duncan Dock are restored to their original design depths.

Dredging is specialised underwater excavation that helps to keep ports and harbours safe and navigable and is a critical aspect of port maintenance.

Isandlwana, which has a 4200m³ hopper capacity, will remove approximately 70,000m³ of material from the sea bed before the end of April. Spoil is pumped into the hopper and can be offloaded by discharging through ten conical bottom valves.

Pumping ashore is also possible by means of either a floating pipeline, a side discharge mechanism or by ‘rainbowing’, where the dredging vessel discharges material that has been claimed from the ocean floor in a high arc to build a land mass elsewhere, such as during nourishment of beaches, to prevent erosion along the coasts or to reclaim land.

TNPA’s fleet renewal programme has boosted the dredging division’s capacity to aid the removal of approximately four million cubic meters of excess material from the seabed every year at South Africa’s ports.

With the most modern equipment available in the specialised service industry, Dredging Services is able to not only meet the needs of the South African port system, but the needs of Southern Africa, helping other African countries grow their economies.

Ships Montly - January 2024

First AirWing Installed on Vectis Progress as Wind Propulsion Gains Momentum

A major milestone in sustainable shipping was reached on 4 March 2025 with the announcement of the successful installation of the first GT Wings...
Advertisement

Related articles

First AirWing Installed on Vectis Progress as Wind Propulsion Gains Momentum

A major milestone in sustainable shipping was reached on 4 March 2025 with the announcement of the successful...

COSCO Shipping takes delivery of new methanol dual-fuel containership

COSCO Shipping has taken a significant step towards sustainable maritime operations by naming its first methanol dual-fuel containership. Following...

Hovertravel Celebrates 60 Years of Service

Hovertravel, the world’s longest-running commercial hovercraft service, is celebrating its 60th anniversary in 2025. As part of the milestone...

BERG efficiency upgrade cuts fuel costs for Norwegian coaster

Lighthouse Ship Management AS has successfully completed a BERG Propulsion retrofit project on one of its managed general...