Construction of the next CSOV for BS Offshore starts at Ulstein Verft

On 11 March 2025, the hull of yard number (Yno) 321 for BS Offshore arrived at Ulstein Verft. This marks the beginning of a new phase in the shipbuilding process.

The vessel is designed by Ulstein Design & Solutions AS for ‘walk-to-work’ (W2W) operations, where personnel walks via a motion-compensated gangway from the ship to a wind turbine.

While the hull has been under construction at the CRIST yard in Poland, closely monitored by a site team from Ulstein Verft, the designers and engineers at the various Ulstein companies in Norway and Poland have been working on finalising the detailed drawings for the ship.

The hull arrival at Ulstein Verft marks a new phase, which includes securing, painting, outfitting, piping, equipment installations, electrical work, and system integration.

The vessel is sister to Yno 320, launched at Ulstein Verft on 23 February.

TWIN X-STERN

Like its predecessor, the newbuild is part of the innovative TWIN X-STERN CSOV series, known for its exceptional operational performance and seakeeping abilities.

During the outfitting phase, the vessel will be equipped with advanced technology, including a 3D-compensated crane and a gangway, ensuring safe and efficient personnel and cargo transfer to offshore wind turbine facilities.

The vessel will also have a diesel-electric propulsion system with substantial battery energy storage, significantly reducing the environmental footprint. She is prepared for methanol as a future fuel.

After her delivery in 2025, the vessel will be ready to support the offshore wind sector with modern, high-comfort accommodation for up to 132 crew and clients.

This is Ulstein’s fifth W2W vessel for BS Offshore. All have been designed by Ulstein Design & Solutions AS and constructed at Ulstein Verft.

BS Offshore is a pioneering ship owner, and Ulstein is proud to continue the partnership, contributing to the advancement of sustainable maritime solutions.

The construction of the next CSOV for BS Offshore starts at Ulstein Verft
The construction of the next CSOV for BS Offshore starts at Ulstein Verft t
Ships Montly - January 2024

Stena Line set to return to normal timetable as Holyhead Port repairs near completion

Stena Line welcomed a statement from Holyhead Port on 8 May 2025 that, following the completion of necessary repairs, Terminal 3 (T3) at Holyhead...
Advertisement

Related articles

Stena Line set to return to normal timetable as Holyhead Port repairs near completion

Stena Line welcomed a statement from Holyhead Port on 8 May 2025 that, following the completion of necessary...

Damen Cape Town delivers third vessel to navy

Damen Shipyards Cape Town (DSCT) has delivered the third Multi-Mission Inshore Patrol Vessel (MMIPV), P1573, at Naval Base...

Finnmarken returns for Hurtigruten

On 16 May 2025 Hurtigruten’s Otto Sverdrop will revert to her former name, Finnmarken. Part car ferry/cargo ship and...

Incat Launches the World’s Largest Battery-Electric Ship

Hundreds of people gathered at the Incat shipyard in Hobart on 1 May 2025 to witness a milestone...