Damen wins refit contract for drilling rig Stena Don

Damen Verolme Rotterdam (DVR), one of Damen Shipyards Group’s most experienced yards in the repair and refit of complex offshore structures, has been awarded a contract by Stena Drilling for a refit of its drilling rig Stena Don.

The vessel will arrive at DVR in October 2018 and is expected to remain there for around three months. The most significant aspect of the works will be the installation of an eight-point mooring system prior to the rig being deployed off the UK’s Shetland Islands.

Preparations are already under way at DVR to ensure that the installation of the mooring system can begin as soon as the Stena Don arrives at the yard. Various elements of the system need to be manufactured.

These include the anchor chain blisters and sponsons which, weighing 1,200 tonnes in all, are currently being fabricated at Damen Shipyards Mangalia, ahead of being transferred to Rotterdam.

Other components of the system that are being prepared include eight anchor winches and the fairleads, plus the winch control cabins which will be supplied by Rolls Royce A.S. Modified VFD switchboards and brake resistor units will be delivered by Siemens A.S. The eight ultra-high-holding power anchors are being supplied by Damen Anchor and Chain Factory.

In addition to the mooring system, the yard will also install strengthening to the hull to comply with the new regulations regarding the mitigation of wave impact forces.

Stena Don, a harsh environment, dynamically-positioned, Class 3 semi-submersible drilling rig, can drill in waters up to 500 metres deep and has accommodation for 120 personnel. 95.5m in length and with a beam of 67m, it was built by the Kvaerner Warnow Werft Shipyard in Germany in 2001.

This will be the drilling rig’s fourth visit to the DVR site. Its most recent stopover was in July 2015 when it came in for a special periodical survey and a mid-life upgrade. The eight-point mooring system will enable the rig to operate over a wider range of water depths and remain longer on station than before, particularly in adverse weather conditions, and will also make it more fuel efficient by not relying solely on the DPS.

 

Ships Montly - January 2024

Viking names newest ocean ship in Croatia

On 29 June 2025 Viking named its newest  ocean ship, Viking Vesta, with a traditional ceremony in Split, Croatia. Serving as ceremonial godmother of...
Advertisement

Related articles

Viking names newest ocean ship in Croatia

On 29 June 2025 Viking named its newest  ocean ship, Viking Vesta, with a traditional ceremony in Split,...

Stena Line announces plans to withdraw its Rosslare-Cherbourg service 

Following a strategic route review, Stena Line has announced that from 30 September 2025, the ferry operator intends...

Deltamarin wins contract for six ro-pax vessels for Grimaldi Lines

On 24 June 2025 Deltamarin signed a design and engineering contract with China Merchants Jinling Shipyard (Weihai) for...

New boxboat Maersk Namsos

Japan's Imabari Shipbuilding successfully delivered Maersk Namsos, a 2,086 twenty-foot equivalent unit (TEU) containership, on 4 June 2025. This...