Advertisement

Fred. Olsen Windcarrier Jack-up Brave Tern completes major crane refit

Brave Tern, the 132m jack-up operated by Fred. Olsen Windcarrier AS, has completed a major crane refit at Damen Shiprepair Amsterdam.

The main operation was the insertion of a 20m section into the main boom of the 800-tonne crane, allowing it to reach a height of 120m. This upgrade now allows it to install and maintain the next generation of wind turbines.

The operation to insert the additional section took 30 days in total. It required the unreeving of all the crane wires before the crane boom could be dropped down to rest on a support structure built from containers.

The boom was then cut in two and the new section inserted and secured using flanges. Following the completion of the new boom the wires were re-reeved and a series of load tests conducted before the crane was certified ready for operations.

To secure the order, Damen Shiprepair Amsterdam (DSAm) offered a fast turnaround time without any loss of quality or attention to detail.

Not only was the project time highly competitive, the actual order was only received the day before the vessel arrived at the yard. However, DSAm had the necessary capacity available and the next few days (a weekend) were spent setting up the project office, building the boom rest structure and positioning the mobile cranes.

It was this ability to both initiate and implement projects at exceptionally short notice (plus its reputation for quality and a convenient location) that convinced Fred. Olsen Windcarrier that DSAm was the ideal yard for this refit. This was the first visit by the Brave Tern to DSAm.

The upgrade of Brave Tern is part of a wider programme by Fred. Olsen Windcarrier to bring both its Jack-Ups up to the standard required to meet the needs of the new generation of 8MW plus wind turbines.

As well as the crane boom extensions, the legs on both vessels have had an additional 14-metres added.

Following the works at DSAm, Brave Tern is now ready to install the latest, high capacity wind turbine generators such as the 8MW MVOW V164. The vessel can carry four complete units (tower, nacelle and blades) per loadout.

Ships Montly - January 2024

Ships Monthly April 2025 issue out now

SHIPS MONTHLY April 2025 The April 2025 issue of Ships Monthly is out now, and is packed with all the usual news and outstanding articles...
Advertisement

Related articles

Ships Monthly April 2025 issue out now

SHIPS MONTHLY April 2025 The April 2025 issue of Ships Monthly is out now, and is packed with all...

Large ammonia-powered ammonia carrier developed by MOL, Namura and Mitsubishi

On 17 March 2025 ClassNK issued an approval in principle (AiP) for a large-size ammonia-powered ammonia carrier, jointly...

Baleària continues to invest in its fleet

In 2024 Spanish shipping company Baleària reported earenings of €130 million, an 11 per cent increase from the...

Stena Line and Norsepower team-up on hybrid ro-ro equipped with Rotor Sails

One of Stena Line’s new ro-pax ferries being built by Jinling Weihai Shipyard in China will feature two...