Advertisement

ISLE OF WIGHT: Wightlink lose damage claim

A claim by Wightlink for almost £1.4 million in damages over ’catastrophic’ engine failures affecting its former Fastcat high-speed vessels was thrown out by the High Court at the end of February. The operator sued Michell Power Systems (MPS),the company contracted to overhaul engines on Fastcat Shanklin, which suffered a major failure in July 2006, before Fastcat Ryde had similar problems the following November.

When the affected engines were sent back to German builders MTU, it was found that clearances between piston pins and pin brushes in each of the 16 cylinders did not comply with manufacturers’ requirements.

Mr Justice Hamblin dismissed Wightlink’s claim and cleared MPS of all liability. He said MPS should have had regard to the recommended clearances and not departed from them without reason. But he added: ’Iam satisfied there were good reasons to do so in this case.’

Ships Montly - January 2024

Ferguson Marine shipyard hands over Glen Sannox

The UK’s first LNG ferry has been completed by Ferguson Marine (Port Glasgow) and was handed over on 20 November 2024. Glen Sannox, the first...
Advertisement

Related articles

Ferguson Marine shipyard hands over Glen Sannox

The UK’s first LNG ferry has been completed by Ferguson Marine (Port Glasgow) and was handed over on...

SAFEEN’s fully electric Damen RSD-E Tug 2513 achieves Guinness World Record

Damen Shipyards Group and its client SAFEEN Group, part of AD Ports Group’s Maritime & Shipping Cluster, have...

Hurtigruten unveils plans for Sea Zero project

Norwegian cruise company Hurtigruten has unveiled updated plans for its Sea Zero project, aiming to launch a zero-emission...

Container vessel orders up by over 50 per cent in 2024

Orders of new container vessels are up by 52 per cent year-on-year, with 254 new contracts placed in...